Data Centre migration strategy: Complete relocation planning guide 2025

Data Centre migration strategy: Complete relocation planning guide 2025

Insights • December 10, 2025 • 10 minutes read

Imagine if you had to move business locations while keeping every facet of your organisation fully operational the entire time. That’s what moving a data centre’s like. The beating heart of every organisation, your data centre powers every login, click, and customer interaction. If anything goes wrong, it’s serious. 

Whether it’s scaling up, meeting compliance, or retiring legacy systems, sooner or later most organisations face a data centre move. And planning one can get overwhelming. After all, every component has to move as one. Miss the beat, and the organisation flatlines, resulting in costly downtime and data loss.  

 According to a 2024 ITIC’s Hourly Cost of Downtime survey, 90% of organisations believe downtime costs them at least US$300,000 (approx: AU$457,000) an hour. These cost estimates are inclusive of lost sales, lost employee productivity, and the potential legal penalties of prolonged outages. For 41% of enterprises, the downtime’s hourly rate is more than US $1 million.   

 Only 4% of organisations surveyed say downtime would cost less than US$100,000 (approx AU$152,000) an hour. Of those, the overwhelming majority (93%) were small organisations with less than ten employees, where downtime costs have an even greater financial impact. Because IT systems directly impact employee productivity, downtime is never free.  

 Those costs are the reason that Gartner says 83% of data migration projects are considered failures. Without a proper data migration strategy, there is a high risk that during the process of transferring data between systems and formats, it can become corrupted, lost or subject to compatibility issues. 

So how can your organisation avoid this? No matter your environment or reason for moving, a comprehensive data centre relocation plan will take away the uncertainty and overwhelm.  

Zero-downtime data centre migration isn’t just possible. It’s the baseline. At least, it should be. With the right data centre migration plan, achieving it is easier than you might think. As a data centre solutions provider, Interactive has orchestrated many successful data centre migrations and relocations over the years. With tailored data centre migration strategies, we’ve helped our customers navigate complex environments, unique requirements, and major challenges to ensure a successful, stress-free move.  

 So if you’re looking for a data centre migration plan that ticks all the boxes, we’ve got you covered. Here’s everything to plan for and consider before the big move to ensure its success. 

Key Insight 90% of organisations believe downtime costs them at least US$300,000 (approx: AU$457,000) an hour.

Understanding Data Centre Migrations

 A data centre migration is when an organisation moves everything that powers its IT system, such as servers, storage, networks, and applications, from one environment to another. 

Depending on the destination and its infrastructure set-up, there are different types of data centre migrations:  

Physical relocation: Moving infrastructure between physical facilities. 

  • When it makes sense: When a new physical data centre location is better suited to your needs. It might be moving your IT infrastructure as part of an office move, or moving to more modern facilities that better meet today’s data centre power and cooling standards.   

 Data centre consolidation: Merging multiple data centres together.  

  • When it makes sense: When you would like to reduce the physical footprint of your data centre network. These types of moves are often associated with organisations that undergo a merger.  

 Colocation migration: Moving to a colocation data centre, either from an on-premise, self-managed data centre or from another colocated data centre.  

  • When it makes sense: For organisations looking to move to a modern data centre that meets reliability and industry standards, without the headache of maintaining this themselves.  

Cloud migration: Moving to cloud storage, whether from a physical or another cloud-based environment. 

  • When it makes sense: For organisations looking take advantage of the flexibility and scalability of cloud infrastructure.  

Virtual data centre migration: A subset of cloud migration that involves moving from physical infrastructure to cloud-based virtualised environments. This is a unique move as it represents a fundamental architectural shift.  

  • When it makes sense: For organisations looking for flexible, scalable IT infrastructure that is easy to manage through   a virtual dashboard, without the need to manage physical hardware.  

 Hybrid migration: A combination of any of the above.  

  • When it makes sense: Allows organisations to leverage the unique advantages of different infrastructure setups, so they can selectively move workloads their best-fit location  

 

Why move a Data Centre?

Moving a data centre is about positioning your organisation where it can perform best.  

Depending on goals and objectives, that can look different in every organisation.  

There are plenty of good reasons why organisations migrate their data centres. If any of these resonate, it might be time to consider that big move.  

 

Your Data Centre migration plan: A complete guide

A data centre migration succeeds when it’s done in steps, not sprints. Each stage builds on the last, turning a complex move into a controlled transition.  

No matter where you’re moving to or from, following a structured migration framework helps reduce downtime and risk. 

Below is a proven five-phase approach, with built-in zero-downtime and compliance strategies designed for Australian organisations. 

 

The Five-phase Data Centre migration framework:

  

Phase 1: Assessment and Discovery (15–20% of the timeline)

The first step is understanding what you currently have. This involves a comprehensive assessment of your existing IT environment, including: 

  • A current state analysis that documents all systems, workloads, and interdependencies. Doing this gives you complete clarity on everything that will need to form part of the migration.  
  • Detailed dependency mapping and application profiling to identify which systems rely on each other. This is where organisations can come unstuck. Just a single dependency that wasn’t accounted for can derail the entire migration.  
  • Baseline performance metrics to measure post-migration success. 

This discovery phase forms the foundation for informed decision-making and helps avoid surprises later in the project. 

  

Phase 2: Design and Planning (20–25% of the timeline)

With the current environment documented, the next step is to design the target state and plan how to get there safely. 

This phase focuses on: 

  • New environment architecture that defines how systems, networks, and storage will operate in the destination data centre or cloud. 
  • Migration runbooks and cutover strategies. These will outlining each migration step, sequencing, and timing to minimise disruption. 
  • Risk-mitigation planning to identify potential points of failure and establish contingency measures. 

Thorough design and planning ensure the migration proceeds predictably, with clear ownership, communication, and fallback options at every stage. 

  

Phase 3: Testing and Validation (15–20% of the timeline)

 Before migrating live systems, thorough testing ensures reliability, stability, and performance in the new environment. 

This phase focuses on: 

  • Pilot migrations to validate tools, methods, and compatibility. 
  • Load testing to confirm the new infrastructure can handle real-world performance demands. 
  • Rollback procedures to guarantee safe recovery if issues arise. 
  • Dress rehearsal execution. This is a full end-to-end simulation of the migration to confirm readiness for cutover. 

Rigorous testing and validation reduce risk, ensuring every system functions correctly before production workloads move. 

  

Phase 4: Execution (20–30% of the timeline)

This is the phase where the migration plan moves from paper to production. Careful coordination and communication are critical to ensure business continuity. 

This phase includes: 

  • A Phased migration approach: transition workloads in manageable stages, minimising disruption to your employees and customers as they rely on the systems.
  • Cutover management to control timing, sequencing, and stakeholder communication during the switch.
  • Real-time monitoring and issue resolution to detect and resolve performance or connectivity issues as they occur. 

 A disciplined execution phase keeps systems stable, users informed, and operations running smoothly throughout the migration window. 

  

Phase 5: Validation and Optimisation (10–15% of the timeline)

After cutover, the final phase focuses on verifying stability, fine-tuning performance, and capturing lessons for future improvements. This phase involves:   

  • Post-migration testing to confirm data integrity, application functionality, and network performance. 
  • Performance tuning to optimise resource allocation, responsiveness, and system efficiency. 
  • Documenting the project’s learnings to record insights, challenges, and successful practices for continuous improvement. 

A structured validation and optimisation phase ensures the migration delivers lasting value through a measurable upgrade in performance and reliability. 

 

Zero-downtime Data Centre migration strategies

For organisations that operate 24/7 or can’t afford service interruptions, zero-downtime migration techniques are essential. These are additional safeguards put in place to ensure systems stay online while workloads transition seamlessly to the new environment. 

 Key zero-downtime strategies include: 

Parallel operating environments. Running both old and new systems simultaneously until full validation is complete during the cutover. 

Failover mechanisms and active-active configurations. Using redundant systems that can automatically switch over if an issue occurs. This assures system availability and performance should any issues arise during the migration. 

Rolling migration approach. Moving workloads in small, controlled batches helps minimise the risk, and potential impact, of downtime disrupting operations throughout the migration process. 

Implementing these strategies ensures that business-critical applications remain accessible, even during large-scale infrastructure changes. 

 

Server Relocation best practices

When physical infrastructure needs to move as part of a data centre migration, planning can be the difference between stability and disaster. To avoid downtime or data loss Each step in the process of moving servers must be planned, documented, and verified. 

Here are the best practices for pulling off a seamless server relocation  

  • Inventory and labelling: Catalogue every server, storage device, and cable to make it quicker and easier reinstallation.
  • Identify decommissioned equipment: Carefully remove any equipment and cables that won’t be relocated.
  • Pre-move backups: Complete and verify backups before any shutdown. 
  • Environmental readiness: Check that the new site’s power, cooling, and connectivity meet operational requirements. 
  • Secure transport: Use professional logistics partners with anti-static, shock-proof equipment handling. 
  • Structured re-commissioning: Power up systems in the correct sequence, validating network and application performance. 
  • Post-move verification: Run performance benchmarks and user acceptance testing to confirm everything works as expected. 

A controlled, well-documented relocation protects critical systems, reduces risk, and ensures a seamless return to full operations. 

 

Data Sovereignty considerations for Australian organisations

Data sovereignty matters when compliance, contracts, or risk policy require Australian control over information. If this applies to your organisation, it’s important to ensure data stays within the right jurisdiction and under the right governance for the entirety of the migration. 

If Australian data sovereignty matters to your organisation, here are the considerations you’ll need to make means:  

  • Confirm the destination data centre or cloud region is physically based in Australia if sovereignty applies. 
  • Avoiding migration tools or replication paths that route data through offshore regions. 
  • Choosing infrastructure and service partners that maintain full administrative control within Australia.  
  • Regulated sectors: Finance, healthcare, and government workloads may also require ASD-certified or Australian-operated environments. 

Ultimately, sovereignty is about control: knowing where data sits, who can reach it, and how it’s managed throughout the move. With a clear migration plan in place, you should have no issues maintaining sovereignty. 

A successful data centre migration comes down to planning, testing, and control. By following a structured five-phase approach, organisations can minimise risk, avoid downtime, and protect critical systems throughout the move. With the right preparation, a data centre migration becomes a measurable upgrade in performance, reliability, and resilience. 

The ultimate test of a successful migration? No one who wasn’t involved could tell you when it happened.  

If you’re thinking about a move, Interactive’s data centre migration expertise turns preparation into success. We’ll help you plan and execute your data centre migration seamlessly and with confidence. To get started, contact our team and let’s work together to bring certainty to your data centre migration.  

[wpforms id="15231"]
[wpforms id="14210"]
FORM HEADINF
Search by industry
  • All
  • Automotive and Logistics
  • Consumer Packaged Goods
  • Corporate
  • Financial Services
  • FMCG
  • Government
  • Healthcare
  • IT, Data and Software
  • Manufacturing
  • Media and Entertainment
  • Real Estate
  • Retail
  • Superannuation
  • Travel